O novo plan de fábrica de Aida Sekkei céntrase no precortado de madeira. O seu concepto trata de crear unha arquitectura que encarna a serie de procesamento da madeira. Inclúe unha pasarela flotante, acristalada, de aproximadamente 100 metros de lonxitude no interior da fábrica, deseñada para que os visitantes poidan observar de preto todo o proceso de precortado. O edificio de oficinas presenta grandes espazos con estruturas de tesoira feitas con materiais de beira biselada, comunmente utilizados como materiais secundarios en casas de madeira. O deseño integra todos os elementos para crear unha fábrica mostra, enfatizando a visibilidade e o atractivo estético en todos os aspectos.
About the A' Design Award de Ouro
Aida Sekkei Precut Fábrica gañou o A' Design Award de Ouro, un recoñecemento inmensamente prestixioso outorgado a deseños de primeira clase, marabillosos e sobresaíntes. Os gañadores Ouro son creacións sumamente innovadoras, visionarias e glamurosamente deslumbrantes que reflicten o xenio, a sabedoría e a destreza dos seus deseñadores. Espérase que Aida Sekkei Precut Fábrica sexa unha invención moi eloxiada, pioneira e monumental que ofrece un valor sen precedentes. Este deseño gañador do A' Design Award de Ouro é un proxecto espectacular e respectado que beneficia moito a arte, a ciencia, o deseño e a tecnoloxía e fai avanzar os seus límites. Aida Sekkei Precut Fábrica crea intensos sentimentos de desexo, esperta a paixón, anima a creatividade e fascina.
Press Kit
- Unique Properties
- This is a project of a new timber processing plant for precut lumber. Its design concept is all about creating an architecture that embodies the series of timber processing. The almost 100-meter-long viewing aisle encased in a random stripe wooden shell is cantilevered and appears as if it floats from the factory building wall. The aim of the impressive façade design with a sense of acceleration and speed is to provoke the image of Aida Sekkei’s further evolution towards the future.
- Dimensions & Packaging
- Site area: 40,023.50 m2
Building area: 14,614.43 m2
Total floor area: 15,206.32 m2
Office Building(2F)
1st floor: 458.21 m2
2nd floor: 429.28 m2
Number of floors: 2 above ground
Height: Maximum height 10.86 m,
Structure: Wooden
Factory Building(2F)
1st floor: 13,886.39 m2
2nd floor: 380.70 m2 - Tags
- architecture, factory, wooden, truss, pre-cut, Factory tour, Japan
- Production Technology
- As for the office, which is the face of the plant, we created one large space by building a scissor truss using members of smaller cross sections (30 mm by 120mm size lumber used as supplementary members such as wall studs of a home). 120mm square Japanese cypress pillars are placed every 303 mm of the wall and to construct load-bearing walls, a 30 mm thick cedar board was inserted between the pillars.
- Design Challenge
- When constructing large-span wooden structures, it's common to use specialized and expensive materials such as large-diameter engineered lumber. However, here, we've achieved a 12-meter span at low cost by combining small-section studs commonly used in typical residential construction to form trusses. This method, the first of its kind in Japan, utilizes these small-section studs (measuring 30×120mm) which are widely used in residential construction.
- Research
- Research Objective: To find a cost-effective method for achieving large spans in wooden structures. Result: The combination of small-section studs into truss structures has enabled the realization of a 12-meter span at low cost. Impact: There is potential for innovative approaches in medium to large-scale wooden construction.
- Inspiration
- Before initiating this design, visiting an existing pre-cut factory left a profound impression. Witnessing the precise, aesthetically pleasing fabrication of columns and beams at remarkable speed sparked inspiration. To capture the dynamism and speed of fabrication observed in the factory, the design concept emerged: a facade featuring a protruding massive timber symbolizing the factory's essence.
- Project Duration
- This project was completed in September 2020 and is currently in operation. The planned site in Bando City is a place where forest resources are abundant despite being near Tokyo. It is conveniently located as a node of the expressway network in the Tokyo metropolitan area.
- Operation Flow
- This is a project of a new timber processing plant for precut lumber designed by Aida Sekkei Co.,Ltd., one of the leading house builders who specializes in traditional Japanese timber construction.
- Patents
- None
- Image Credits
- Image #1-#5: Photographer Nobuaki Miyashita, Variations, 2020