Aida Sekkei Precut Fabbrika by Nobuaki Miyashita is a highly esteemed winner of the very prestigious 2024 Premju A' Design Award tad-Deheb in Disinn tal-Arkitettura, Bini u Strutturi Competition Category.
DehebArkitettura· 2024
Aida Sekkei Precut Fabbrika
Client: Aida Sekkei Co., Ltd.
Premju A' Design Award tad-Deheb Winner in Arkitettura Category
- 148,971
- Verified Award Winner
- Verify Award Status for #160159
The Design
About Aida Sekkei Precut Fabbrika
Il-pjan tal-fabbrika l-ġdida ta' Aida Sekkei jiffoka fuq il-qtugħ minn qabel tal-injam. Il-kunċett tagħha huwa kollu dwar il-ħolqien ta' arkitettura li tgħakkes is-serje ta' proċessar tal-injam. Din tinkludi mixja li tiżfen, magħluqa bil-ħġieġ, ta' madwar 100 metru fit-tul ġewwa l-fabbrika, iddisinjata biex il-viżitaturi jkunu jistgħu josservaw mill-qrib il-proċess kollu tal-qtugħ minn qabel. Il-bini tal-uffiċċju għandu spazji kbar bi trassi magħmula minn materjali feather edge, li normalment jintużaw bħala materjali sussidjarju fid-djar tal-injam. Id-disinn jintegra l-elementi kollha biex joħloq fabbrika ta' wiri, li tenfasizza l-viżibbiltà u l-appell estetiku f'kull aspett.
The Recognition
About the Premju A' Design Award tad-Deheb
Aida Sekkei Precut Fabbrika huwa rebbieħ tal-Premju A' Design Award tad-Deheb, rikonoxximent prestiġjuż ħafna mogħti lil disinji tal-ewwel klassi, mill-isbaħ u eċċellenti. Ir-rebbieħa tad-Deheb huma ħolqien innovattiv ħafna, b'viżjoni u li jleqqu b'mod li jgħammex, li jirriflettu t-talent, l-għerf u l-ħila tad-disinjaturi tagħhom. Huwa mistenni li Aida Sekkei Precut Fabbrika ikun invenzjoni mfaħħra ħafna, li tistabbilixxi x-xejriet u monumentali li tagħti valur bla preċedent. Dan id-disinn rebbieħ tad-Deheb huwa proġett spettakolari u rispettat li jwessa' l-fruntieri tal-arti, ix-xjenza, id-disinn u t-teknoloġija. Aida Sekkei Precut Fabbrika joħloq xewqa qawwija, iqajjem il-passjoni, iħeġġeġ il-kreattività u jisħer lilna.
Behind the Design
Press Kit
Credits, team members and technical details provided by the designer.
- Unique Properties
- This is a project of a new timber processing plant for precut lumber. Its design concept is all about creating an architecture that embodies the series of timber processing. The almost 100-meter-long viewing aisle encased in a random stripe wooden shell is cantilevered and appears as if it floats from the factory building wall. The aim of the impressive façade design with a sense of acceleration and speed is to provoke the image of Aida Sekkei’s further evolution towards the future.
- Dimensions & Packaging
- Site area: 40,023.50 m2
Building area: 14,614.43 m2
Total floor area: 15,206.32 m2
Office Building(2F)
1st floor: 458.21 m2
2nd floor: 429.28 m2
Number of floors: 2 above ground
Height: Maximum height 10.86 m,
Structure: Wooden
Factory Building(2F)
1st floor: 13,886.39 m2
2nd floor: 380.70 m2 - Tags
- architecture, factory, wooden, truss, pre-cut, Factory tour, Japan
- Production Technology
- As for the office, which is the face of the plant, we created one large space by building a scissor truss using members of smaller cross sections (30 mm by 120mm size lumber used as supplementary members such as wall studs of a home). 120mm square Japanese cypress pillars are placed every 303 mm of the wall and to construct load-bearing walls, a 30 mm thick cedar board was inserted between the pillars.
- Design Challenge
- When constructing large-span wooden structures, it's common to use specialized and expensive materials such as large-diameter engineered lumber. However, here, we've achieved a 12-meter span at low cost by combining small-section studs commonly used in typical residential construction to form trusses. This method, the first of its kind in Japan, utilizes these small-section studs (measuring 30×120mm) which are widely used in residential construction.
- Research
- Research Objective: To find a cost-effective method for achieving large spans in wooden structures. Result: The combination of small-section studs into truss structures has enabled the realization of a 12-meter span at low cost. Impact: There is potential for innovative approaches in medium to large-scale wooden construction.
- Inspiration
- Before initiating this design, visiting an existing pre-cut factory left a profound impression. Witnessing the precise, aesthetically pleasing fabrication of columns and beams at remarkable speed sparked inspiration. To capture the dynamism and speed of fabrication observed in the factory, the design concept emerged: a facade featuring a protruding massive timber symbolizing the factory's essence.
- Project Duration
- This project was completed in September 2020 and is currently in operation. The planned site in Bando City is a place where forest resources are abundant despite being near Tokyo. It is conveniently located as a node of the expressway network in the Tokyo metropolitan area.
- Operation Flow
- This is a project of a new timber processing plant for precut lumber designed by Aida Sekkei Co.,Ltd., one of the leading house builders who specializes in traditional Japanese timber construction.
- Patents
- None
- Image Credits
- Image #1-#5: Photographer Nobuaki Miyashita, Variations, 2020
Sponsored
Explore Beyond Designers.org